Culley Station
Newburgh, Indiana
For the engineering, procurement and construction of a
limestone unloading, storage and reclaiming system at their
Culley Station, the Southern Indiana Gas & Electric
Company selected Roberts & Schaefer for complete construction
management under a turnkey contract.
Limestone is delivered on river barges and unloaded by
a clamshell type barge unloader. The unloaded material is
delivered to a receiving hopper located on a floating barge
where it is carried by a belt conveyor to a combination
loadout and storage facility. The material is transported
via five additional transfer conveyors to the limestone
day silo. Each transfer station is equipped with an independent
dust collecting system. The project was completed in approximately
13 months.

|