Roberts & Schaefer provided engineering and equipment
procurement services for system upgrades to the coal handling
facilities for Illinois coal-fired power plants Fisk Station,
Waukegan Station, and Joliet No. 9 Station.
The Waukegan Station project consists of constructing a
new 200 ft. long, rail-mounted stacker with a rear pivot
mount and articulating boom. Design capacity is a 1800 TPH,
fully-automated stacker that gives ComEd the ability to
form a 44-foot high 16,000-ton coal storage pile.
The Joliet No. 9 Station project consists of a new counterweighted
pedestal mounted stacker. Design capacity is 1,600 TPH,
and allows ComEd to form a 45 foot high 23,000 ton coal
storage pile shortening the train unloading time by about
50%.
|