ROBERTS AND SCHAEFER COMPANY - How the world processes its resources


Coal Handling & Preparation Facility

Wyoming Fuel Company
New Elk Mine
Weston, Colorado

Roberts & Schaefer provided detailed engineering services for Wyoming Fuel Company's New Elk Mine coal handling and preparation facility near Weston, Colorado.

R&S began phase one by preparing layouts of the general arrangement of the entire facility, establishing the most cost-effective plant configuration to fit the terrain and integrate into the existing facilities.

The layout of the 400 TPH preparation plant was based on a flowsheet prepared by Wyoming Fuel Company. The plant uses a heavy media vessel to clean the coarse coal fraction and diester tables to clean the one-quarter inch by 100-mesh fraction. The plant can be expanded to double its feed rate.

Phase two provided the detailed design of the preparation plant, including foundation support system, structural steel design, platework detailing for chutework, sumps and other material and slurry handling systems, process piping flowsheets and detailed process piping and utility piping.